Generating ISL Job Progress Report

You can generate the job progress report for Windows and Linux isolation jobs. The isolation job details are included in the report.

Complete the following steps:

  1. Go to the Jobs tab, click the Windows or Linux tab based on the report you want to generate, and then click View Progress from the Quick Actions menu of the job.
  2. Click the Download download icon.  icon from the "Job Progress" page, a Generate Report window is displayed. 

    Generate Report window for the isolation job progress


    - You cannot generate the fifth report if the four reports you generated are in the "Generating" or "Queued" state. 
    - You cannot generate the same report again if you apply a filter from the "Job Progress" page and the report is in the "Generating" or "Queued" state.

  3. Enter the name and description of the report.
  4. Select the report format you want to download. You can download the report either in CSV or PDF format. 

    PDF reports support the selection of up to 5 columns for optimal readability.

  5. If you select CSV format, by default, all columns are pre-selected that are generated in the report. To customize your selection, select only the required check-boxes for the columns that you want to generate in the report. 
  6. Click Generate Report. The Report Generation message is shown, which mentions that the data is downloaded in CSV format. 

    report generation message.

    If four reports are in the "Queued" or "Generating" state, the following message is shown: 

    Message shown when four reports are queued or generating

  7. Click the Report List link from the Report Generation message (as shown in above image) to see the report's status. 
  8. Click the Download Download icon. icon from the Actions column on the Reports > Reports tab. Note that the Download icon is enabled only when the report status is Ready. 

    Reports tab showing the job progress report status

 A list of only ten reports is shown and the report shown in the list is available for download only seven days from the report generation date.

The report is downloaded as a zip file. After you extract the zip file, you can see the report in CSV/PDF format based on your selection.